Turning parking into a protected area

Project characteristics

Project designation:

Training and adaptation of an above-ground parking lot to a protected space in a private house.

The area of the building is 18 m2 net

Construction method:

Type: residential protective building

Preparation of the building: The construction was carried out in a residential area and included the demolition of external block walls, demolition of the floor, pouring of the floor and walls due to a new structural solution and the addition of protective frames (door and window) for maximum protection.​

Planning: planning was carried out by defense planning company A - S.I.P.H. in accordance with the standards of the Ministry of Defense.​

Placement: The building was placed on a pre-prepared territory according to the model that was given to the customer.​

Accessories:

Door protection: stairwell plinth protection and door replacement.​

Protective frames: replacement, addition and adjustment of accessories in the parking area and their adaptation to the standards of the Ministry of Defense (front windows - gas sights, pipes).​

Building accessibility: The building is not adapted for people with disabilities.​

Auxiliary accessories: connection of a new electrical system, including emergency lighting fixtures.​

Gas tightness: without gas tightness.

Delivery package to the customer: includes plans for standard signs for frames and electrical approval, laboratory tests

Delivery to the customer:

Execution time: 21 days.

Delivery date to the customer: November 2019